Weston, WV — Rehabilitation of Failed Corrugated Metal Pipe

Weston, WV CMP Culvert

Our purpose is to help customers choose solutions which will insure that the process fits the application and do this reliably and cost-effectively. All information in this field report will assist the engineer to reduce cost and minimize future maintenance costs.
Abstract
Most of the existing corrugated metal pipe (CMP) installed as culverts under our roadways are reaching the end of their working life. There is an emerging widespread need to address this problem in an economical way that minimizes traffic disruption. West Virginia DOT considered replacing deteriorated CMP culverts. This Field Report presents an existing application where a deteriorated culvert was rehabilitated using Snap-Tite HDPE Pipe.

Read more